KMC performed critical infrastructure development to help get the Muskeg River Mine underway by removing muskeg and completing initial site grading of the plant site area.  From October 1999 to April 2000, KMC moved over 5.5 million cu. metres of muskeg and topsoil material under challenging work conditions.

KMC was able to mobilize additional equipment from its nearby operations to meet Albian’s requested construction schedule despite an increase in volumes of 270%.